El Niño is driving extreme heat and water stress across Southeast Asia. Ho Chi Minh City and Bangkok already rank among some of the most heat-risk cities in the world, according to a 2026 Oxford University study, as temperatures compound with humidity and dense urban populations across the region.
This heat risk is converging with one of Southeast Asia’s fastest-growing industries: data centres. For data centre developers and owners in the region, extreme heat and reduced rainfall strain water supplies and electricity generation, and when those fail, cooling systems follow, leading to business interruption.
This same pressure runs through the digital infrastructure ecosystem including telecommunications networks, semiconductor manufacturers, equipment suppliers, and utilities. Construction and operational phases carry different exposure, each with its own risk and its own response.
Heat and water stress can hit a construction site in three ways:
Every lost day pushes handover later, postponing revenue while financing costs run on. A contractor may require an extension of time for weather beyond its control, relieving them of delay penalties, but the owner can still face liquidated damages from their own tenant or offtaker for late delivery. Delay in start-up insurance generally responds only where there is insured physical damage, so a heat-driven stoppage may leave that exposure uninsured.
Operational uptime is shaped from the planning and site selection stage, when it’s most cost-effective to model a site against future energy and utility challenges. Once a facility is live, the exposure moves outside the fence. Three dependencies come under pressure together:
When El Niño-driven disruption stops short of physical damage, conventional business interruption insurance may not respond — and utility or supplier extensions vary by wording, leaving operators exposed to uninsured revenue loss and SLA breach liability.
The risk does not end when El Niño does. When El Niño gives way to La Niña, the risk profile shifts from heat and drought to heavy rainfall and flooding which can affect drainage, substation design, placement decisions, and continuity plans across the entire operation.
Marsh provides data-driven insights and risk capabilities across the digital infrastructure and data centre lifecycle — from site selection and construction to operations — trusted by leading developers and operators.
El Niño is expected to strengthen through early 2027, so the window for decisions that change the outcome is now. Request a Marsh climate risk assessment for your data centre to identify where heat, water shortages, and utility disruption could exceed construction contingencies or operational tolerances, and where to prioritise mitigation, continuity, and insurance decisions.