Why time to power is now more critical than cost of power

Behind-the-meter power for data centers.

The digital infrastructure boom is reshaping the power conversation

Demand for data centers, cloud capacity, AI workloads, semiconductor fabrication, and advanced logistics facilities is accelerating across major markets. But utility infrastructure is struggling to keep pace with this growth. As a result, behind-the-meter (BTM) power is evolving from a backup solution to a core project enabler.

BTM power refers to generation or storage located on the customer’s side of the utility meter. It can include onsite gas-fired generation, batteries, solar, fuel cells, or microgrids configured to serve a facility directly. Historically, these systems were often viewed as niche or supplemental. Today, they are becoming central to how digital infrastructure projects in the US are planned, financed, and delivered.

The quest for speed is fueling BTM power

The underlying driver of BTM is speed. Large data center campuses now require enormous amounts of electricity, and the growth of generative AI is pushing those requirements even higher. In some markets, developers are seeking hundreds of megawatts for a single site. 

Yet, most utilities face long interconnection queues, transmission bottlenecks, substation constraints, and lengthy upgrade timelines. Even where grid power may ultimately be available, it is unlikely to provide the energy needed within the timeframe required by developers, investors, or customers.

That is why time to power has become more important than cost of power.

For digital infrastructure developers, a delayed energization date can mean missed leasing commitments, stranded capital, deferred revenue, and lost market share. In a world where hyperscalers and enterprise customers need capacity immediately, waiting years for full utility service may not be commercially viable. A power solution that is more expensive on a per-kilowatt-hour basis can still create greater enterprise value if it allows a facility to open and scale on time.

BTM power helps close that gap. It can provide bridge power until utility capacity is available, or it can become part of a permanent operating model that supports baseload demand, redundancy, resilience, or peak management. 

In either case, it gives owners more control over schedules and helps reduce dependence on grid upgrades that are outside data center owners’ and developers’ control.

At the same time, BTM power introduces risks that need to be assessed early. Key considerations include: 

  • Permitting and environmental approval risk, especially for gas-fired assets
  • Fuel availability and price volatility
  • Equipment lead times
  • Construction and commissioning delays
  • Operational reliability once the system is live 
  • Stakeholder concerns related to emissions, water use, or noise

From a risk management perspective, owners should evaluate contractual allocation of responsibility among developers, utilities, EPC contractors, and equipment suppliers, along with property, business interruption, and cyber-physical exposures tied to more complex onsite energy systems.

The broader point is that power availability has become a critical path issue for the US digital economy. In constrained markets, access to megawatts can determine whether a project gets built, leased, and scaled. As competition for compute capacity intensifies, BTM power is becoming more than an energy option; it is a tool of execution. That’s because, in this market, the value of power increasingly depends on how quickly it can be delivered.

Speak with a Marsh digital infrastructure specialist about how to protect capital, strengthen resilience, and support better decisions.